Sidewalk and Lane Closure
on Mario Capecchi Drive

.

Sidewalk Demo/Placement Plan Lane Closure: Friday, June 21st 1:00pm-3:30pm & Saturday, June 22nd 7:00am-12:00pm.

Sidewalk Closure: Friday, June 21st 1:00pm – Sunday, June 23rd 7:00am.

Timeline

Friday, June 21st 1:00pm: Close crosswalk/sidewalk and traffic lane as depicted in the image.

  • Jacobsen construction will remove fence panels to allow equipment access for sidewalk demolition.
  • Excavation contractor will remove a portion of the existing sidewalk and place in dump trucks.
    • Dump trucks will be located in the west lane on Mario Capecchi.
  • Excavation contractor to bring in road base and disperse as needed at location of future sidewalk.
    • Dump trucks will dump road base from west lane on Mario Capecchi.

3:30pm: Open the road and stage the traffic control barricades in gutter (crosswalk/sidewalk closure to remain).

  • Excavation contractor will finish grading for sidewalk.
  • Concrete contractor will possibly begin placing formwork.

Saturday, June 22nd 7:00am: Close 1 lane of traffic in the same fashion as Friday’s closure.

  • Concrete contractor to form/pour sidewalk and approach.

12:00pm: Open the road and stage the traffic control barricades in gutter (crosswalk/sidewalk closure to remain).

7:00am: Barricade contractor to remove all traffic control (including sidewalk closure signs).

Contact Info

Shireen Ghorbani

  • Communication Specialist
  • office: 801.581.6077
  • Send email