Salt Lake Station Center Remediation Project

Project Overview:

EPA and University funded project to clean up a contaminated 2-acre plot (550 and 570 West 400 South) in Salt Lake City’s Rio Grande District.

About the Project


Key Project Milestones and Tentative Timeline 

May 2025: EPA Brownfield Cleanup Grant Award Announcement 

September 2025: EPA Grant Co-operative Agreement and Award finalized with EPA 

June 2026: Cleanup Contractor Selection Completed 

July-September 2026: Site prep and Corrective Action Finalization 

September-October 2026: Remedial Activities 

October 2026 through December 2027 - Post-remediation Environmental Monitoring

September 2029: EPA Grant Budget Period Ends 

Public Meeting and Comment

The University of Utah will host periodic virtual public meetings to share information about the cleanup project’s progress and answer questions from the community. 

Community Meeting June 26, 2026 
Upcoming meeting TBD 


Contact Information:

Amit Nair, Environmental Health and Safety

amit.nair@ehs.utah.edu

Eric Newby, U Facilities

eric.newby@utah.edu

Troy Robbs, Real Estate Administration

troy.robbs@utah.edu

 

Last Updated: 10/2/26